Witherell Musum of Technology (WMT) provides the following data on the costs of maintenance and the number of visitors for the last four quarters:
Number of Visitors per Quarter Quarterly Staffing Costs
12,825 $ 404,850
15,706 461,500
14,099 425,850
6,675 464,910
Use the high-low method to estimate the fixed cost of quarterly staffing and the staffing cost per visitor. The museum expects a record 22,550 visitors next quarter because several new conventions have been scheduled. What would be the estimated staffing costs?