If one of the activities on the critical path is​ delayed, the entire project will be delayed.
b. the critical path is the sequence of activities between a​ project's start and finish that takes the shortest time to complete.
c. there may be more than one critical path in a project network.
d. the activities along the critical path determine the completion time of the project.

Respuesta :

must be d all activities must be completed for project completion