Respuesta :
Answer:
Fabricating Department = $136470= 53000 +total 49100 of $1.7 per direct labor hours
Assembling Department = $$ 90,410= 43000 +total 43100 of $ 1.10 per direct labor hours
Explanation:
When a fixed line intersects a vertical axis at the point of total budgeted cost line represents total cost of the activity . From this we can calculate the following.
Fabricating Assembling
Total Cost for 46100 DLH $131,370 $93,710
Fixed Costs (53000) (43,000)
Variable Costs 78370 50,710
Variable Cost Per hour 78370 / 46100 50,710 / 46100
= $ 1.7 = $1.10
Fabricating Assembling
Total DLH 49100 43100
Variable Cost Per hour $ 1.7 $1.10
Variable Costs $ 83470 $ 47410
Fixed Costs 53000 43,000
Total Budgeted Cost 136470 $ 90,410