Respuesta :
Answer:
King Corporation
a. Computation of total budgeted manufacturing overhead cost:
Activities Standard Deluxe Total
Materials handling (number of parts):
Standard = 8 x $4 x 1,000 $32,000
Deluxe = 10 x $4 x 1,000 $40,000 $72,000
Machine setup (number of parts):
= 20 x $375 $7,500 $7,500 $15,000
Insertion of parts (number of parts):
Standard = 8 x $28 x 1,000 $224,000
Deluxe = 10 x $28 x 1,000 $280,000 $504,000
Finishing (direct labor hours):
Standard = 2 x $54 x 1,000 $108,000
Deluxe = 3.5 x $54 x 1,000 $189,000 $297,000
Total $371,500 $516,500 $888,000
b. Computation of the manufacturing overhead cost per wheel of each model using ABC:
Standards = $371,500/1,000 = $371.50
Deluxe = $516,500/1,000 = $516.50
c. Computation of the company's traditional plantwide overhead rate to determine manufacturing overhead cost per wheel:
Overhead rate = $888,000/6,000 = $148
Manufacturing overhead cost per wheel:
Standard = $148 x 2.6 = $384.80
Deluxe = $148 x 3.4 = $503.20
Explanation:
a) Calculations:
Total overhead cost = $888,000
Allocation based on total direct labor hours per wheel
Plantwide overhead rate:
Total labor hours:
Standard 2.6 x 1,000 = 2,600 hours
Deluxe 3.4 x 1,000 = 3,400 hours
Total labor hours = 6,000 (2,600 + 3,400)
= $888,000/6,000 = $148 per direct hour
b) According to wikipedia.com, "Activity-based costing is a costing method that identifies activities in an organization and assigns the cost of each activity to all products and services according to the actual consumption by each. This model assigns more indirect costs into direct costs compared to conventional costing."