Answer:
$2,450 Unfavorable
Explanation:
The computation of material price variance is shown below:-
Material price variance = ( Standard Price - Actual Price ) × Actual Quantity of materials purchased
= $17.40 - ($124,250 ÷ 7000) × 7,000
= ($17.40 - $17.75) × 7000
= $2,450 Unfavorable
Therefore for computing the material price variance we simply applied the above formula.