Question: What Is The Average Time Spent Per Outsourced Project, Across All Regions For All Of The Projects? Bentrim Outsourcing. See attached.

Based on the time spent per project and the number of projects, the average time spent per outsourced project is 271 hours.
The time spent on all the projects can be found by the formula:
= ∑( Number of projects in continent x Average time per project)
Solving gives:
= (13 x 278) + (6 x 382) + (4 x 279) + (7 x 148) + ( 3 x 298)
= 8,952 hours
= ∑Projects per continent
= 13 + 6 + 4 + 7 + 3
= 33 projects
This is then found as:
= Time spent in total / Number of projects
= 8,952 / 33
= 271 hours
In conclusion, 271 hours was spent on average.
Find out more on outsourcing at https://brainly.com/question/4456416.