Question: What Is The Average Time Spent Per Outsourced Project, Across All Regions For All Of The Projects? Bentrim Outsourcing. See attached.

Question What Is The Average Time Spent Per Outsourced Project Across All Regions For All Of The Projects Bentrim Outsourcing See attached class=

Respuesta :

Based on the time spent per project and the number of projects, the average time spent per outsourced project is 271 hours.

Time spent on all projects

The time spent on all the projects can be found by the formula:

= ∑( Number of projects in continent x Average time per project)

Solving gives:

= (13 x 278) + (6 x 382) + (4 x 279) + (7 x 148) + ( 3 x 298)

= 8,952 hours

Number of projects

= ∑Projects per continent

= 13 + 6 + 4 + 7 + 3

= 33 projects

Average Time Spent

This is then found as:

= Time spent in total / Number of projects

= 8,952 / 33

= 271 hours

In conclusion, 271 hours was spent on average.