Z is the preferred service level, it is the usual deviation of lead time, and D avg is the demand common. do not be intimidated. The best technique for calculating safety inventory only calls for a four-step procedure to calculate these variables.
Solution:
Stock out level=4%
In-stock Probability=100-4=96%
Therefore Z value at 96% service level=1.751
Resulting Z -a value of 1.751.
A stockout situation. With a lower score approach, you may have higher possibilities of running out of inventory. as an example, in case you pick out a Z rating of 2.33, there's a ninety-nine percent threat that you might not face a stockout situation. assume an agency has a team to investigate the market call, and it has been estimated that the call for an umbrella is almost 1000 devices each month. As a precaution, the organization can determine to have a hundred units as protection stock because the call for is in no way constant.
Learn more about Safety stock here:-https://brainly.com/question/4155499