A developer is planning a building containing 103,000 square feet. construction cost are estimated at $42 per square foot; 90% financing is available. how much money must the developer put up to complete the project

Respuesta :

Answer:

$432,600

Step-by-step explanation:

Given:

Total square footage: 103,000 square feet

Construction cost per square foot: $42

Financing available: 90% (90% = 0.9)

How much money must the developer put up to complete the project?

First, we calculate the total cost of construction.

103,000 · 42 = $4,326,000

Next, we calculate the financing amount.

4,326,000 · 0.9 = $3,893,400

Final. we subtract the financing amount from the total construction cost to find the money the developer must put up.

4,326,000 - 3,893,400 = $432,600

So, the developer must put up $432,600 to complete the project.